Update Re: Abatement and Deconstruction of old LMST

Date: September 24, 2016 Author: Cathy Gibson Categories: News & Events

LMST_Construction_sm

On Sept. 23, 2016 the following update was sent by the NS Department of Transportation and Infrastructure Renewal (NSTIR) to parents and neighbours about the abatement and deconstruction of the former LMST building on Watt Street:

 

Nova Scotia Transportation and Infrastructure Renewal
Building Project Services Dvision
Engineering, Design & Construction

NOTICE REGARDING THE LeMARCHANT ST. THOMAS SCHOOL


Nova Scotia Department of Transportation and Infrastructure Renewal (NSTIR) has awarded a contract to Dexter Construction for the regulated materials abatement and deconstruction of the existing school. The work also includes the construction of a temporary access driveway along the east side of the existing sports field that will provide access to the construction site during demolition activities and the construction of the new school.

Work to install the site fencing is scheduled to begin on Monday, September 25th, The regulated materials abatement will begin the first week of October and will continue until January 2017. Deconstruction of the existing building is scheduled to begin mid-December and will continue until the end of January 2017. The entrance to the temporary access driveway is expected to be installed in October, however the driveway proper is not expected to be installed until mid- November.

Dexter Construction will make every effort to minimize impacts from the construction process on adjacent neighbours during construction. Michael Parrot or Steve McCall, Dexter’s project management representatives may be contacted at 902-478-2675 (Michael) or 902-420-6478 (Steve) regarding concerns pertaining to construction related issues. During times of active construction activities, the public should expect to receive a response to telephone calls within 24 hours, and during evenings and weekends, calls will be returned early the next business day. If for some reason there is an urgent concern and the Dexter representatives cannot be reached, residents may also contact Dexter’s head office at 902-835-3381.

If you have questions regarding this new school project in general, or if a response to a concern is not received as outlined above, please contact Krista Stevens of Nova Scotia Transportation and Infrastructure Renewal during regular business hours at 722-1207.

Yours truly,
Krista Stevens, P.Eng.
NSTIR Project Manager